Málaga planetarium back on track. New investors step in after six years of delay
Diario Sur reports that new local and foreign investors have struck a deal with the concession holders to revive Málaga's long-stalled planetarium, with works permit paperwork moving again.
By Costa del Sol Journal Newsroom · · AI-assisted

Málaga's long-delayed planetarium project is moving again after six years of inactivity. Diario Sur reported that new local and foreign investors have reached an agreement with the concession holders to get the scheme off the ground, and its English edition, SUR in English, carried the same account.
The building is planned on a council-owned plot next to the Campamento Benítez site and the Ikea shopping centre. It matters to anyone following Málaga's cultural and tourism offer, and to the city's finances, because the project carries an annual payment to the council.
Key facts
- Site: a municipal plot of 8,800 square metres beside Campamento Benítez and Ikea, with a planned building of 4,500 square metres.
- Concession: won in a 2020 tender by a consortium of Málaga engineering firm Gestomer, astronomer Alberto Castro Tirado and the multinational Sky-Skan.
- Cost: the project has been valued at around ten million euros, according to Diario Sur.
- Trees: the works involve removing 234 trees and transplanting ten more, with a 75,283-euro deposit required for replanting on the same plot.
- Annual payment: the winning bid for the land was 115,000 euros a year.
Why the project stalled
According to Diario Sur, the concession was originally proposed by a company from Jaén, AstroÁndalus. Another bid came from Málaga Planetarium, the company that won the tender in 2020.
Since then, the financial difficulties of the concession holders have held the project back. Diario Sur said the new investors have told town hall officials about their agreement with the concessionaires.
The papers had also stalled. The works licence was granted but never formally issued, because several conditions were outstanding. The developers had a maximum of six months to meet them.
In May 2024 they asked for an extension, citing what the government team, in a reply to the opposition group Con Málaga, described as the "complexity and singularity of the approved project". In August of last year the council's licensing service sent a formal notice giving them 15 days to comply or respond.
What has changed
Diario Sur, citing sources, said the developers submitted the detailed construction project, endorsed by the Colegio de Arquitectos (architects' association), to the Gerencia Municipal de Urbanismo (the town hall's planning department) several weeks ago. That was one of the outstanding conditions.
The newspaper's sources also said the 75,283-euro deposit for replanting trees is expected to be paid in the coming weeks, so that planning could issue the works permit soon.
The licence has still not been issued, so the three-month period set in the tender for works to start has not begun. Diario Sur said the developers' failure to meet the conditions had allowed the council to revoke the permit, but officials preferred to wait until funding was secured.
The transfer of the plot to the promoters has also not been formalised, according to information the council gave Con Málaga last year. The council had asked for documents and for the annual payment to be up to date. Diario Sur reported that the new funding should let the promoters carry out the works and pay the fee to secure the land.
The paper noted that the owners had said several times in recent years that they were close to securing financing.
What is planned
Diario Sur said the centrepiece will be a 27-metre dome with a 430-seat tiered auditorium. Sources told the paper this would make it the fourth-largest planetarium in the world and the main reference in south-west Europe.
The building is described as family entertainment and science outreach space, with more than 100 parking spaces. Annual visitor numbers are estimated at half a million.
It would use large LED screens with resolution above 8K, developed with Sky-Skan International. The plans also include interactive STEAM workshops, holiday camps, permanent and temporary exhibitions, and talks by international scientists. The main hall could also host concerts, corporate events and scientific meetings.
What to watch
The next steps are the payment of the tree deposit and the issuing of the works licence by the planning department. Those are the points to check with the Ayuntamiento de Málaga (city council), as the report relies largely on unnamed sources.